Batting: January 17, 2020
On a busy, windy and snowy day,
it was the insulation crew in the starring role.
Alberto's stonemasons finished the pillar off the office.
The carpenters framed out the tub deck in Bathroom D.
And Bob Rowe's crew focused on the ductwork up in the attic.
But mainly it was the insulation crew installing the batting.
In the sewing room . . .
. . . and the laundry room, installing the batting really defines the rooms now.
Down the hallway, and going up the stairs.
In the back bedroom.
The master closet.
Batting insulation is nestled around the ductwork above the office.
And 8-inch thick bats are placed above the master bedroom ceiling.